Once a new work order has been created, the Work Order Creation interface will be displayed. This interface will allow you to select products and set specific options and properties for the work order.
- Configure Name – Allows you to change the name of the work order, or create a field-driven name.
The work order name can also be edited directly in the "Work Order Name" textbox.
- Select Recent Name – A drop-down of previously used names in the Work Order Creation UI.
- Properties – Allows you to access and modify the work order properties (name, number, comments, etc.)
- Products by Work Order – Allows you to filter the tree view to display only the products pertaining to a selected work order.
- Parts Group – Allows you to select a group to assign to each part. When the parts are processed, a separate work order is created for each group. So, for example, if you wanted to do all fronts as a group, drawer parts as a group, carcass parts as a group, and adj shelves as a group, you'd set up the mapped stations with 4 different parts group assignments. Part Mapping is set via the Product Library and can be used to set parts to go to processing stations automatically.
- Default Status* – Allows you to select the status of the work order.
- Print Work Order Report Groups – Turns on the ability to generate report groups.
- Process Flatshot Tokens – Turns on the built-in flat shot tokens, which can be used in reports with dynamic product images.
- Auto Assign Station Rules - This box automatically applies rules for assigning parts to processing stations.
- Auto Assign Map Parts - This box automatically assigns parts to processing stations configured with the map parts function.
- Create DXF Files – Turns on the ability to create individual DXF files for each part.
- Create WMF Images for All Parts – Turns on the ability to create image files for all parts which can be used in reports and labels.
- Calculate Multipliers* – Turns on the ability to calculate efficiency multipliers to estimate work order time and costs.
- Project Tree – Allows you to select the product(s) to be processed. Selecting the parent category (project, category, or room) will select all the products within it.
- Hide Previously Processed Products – Allows you to filter out products that have already been processed.
Intended for specific ERP applications.
Related Articles
Understanding Work Orders
Understanding Work Orders Work orders are used to send product information to the shop for manufacturing and assembly. There are multiple ways to create work orders. The first option allows you to select the products to process from a tree view. The ...
Work Order Naming
Work Order Naming Work orders can be set up to use a standardized naming convention using variables (fields). You can also add a custom name for each work order created. Without setting this up, the default name will be a date/time stamp. When using ...
Work Order Preparation
The Product List is the best way to ensure that the products for a room or project are correct before creating a work order. The Product List shows more information about the products than the work order interface displays. Before creating a work ...
Modify Work Order Interface
As of build 20.1.608.641, there is a Modify Work Order interface that allows users to make changes to work orders more conveniently. Access the interface: Open a work order in the processing center. Select General > Modify Work Order. Fig. 01 – ...
Processing Work Orders and Processing Center
Processing Work Orders/Processing Center Once the products have been selected, and the work order properties and options have been set up, click the Process button to continue with the work order. After the processing has finished, a window will be ...
Recent Articles
Microvellum Foundation Library Release Notes | Build 26.0220
The following release notes apply to the Microvellum Foundation Library build 26.0220. Additions Added DTC Magic Pro and Magic Star Ultra drawer systems. Magic Pro Items added in hardware file 300 and 600 lengths for all drawer heights. Add 60kg ...
Microvellum Release Notes | Build 25.2.0223.641
The following release notes apply to Microvellum build 25.2.0223.641. Add 2D Elevation Tokens to 3D Drawings Fig. 1: The new 2D Elevation setting. A popularly requested feature by the community has been added to the Microvellum software: the checkbox ...
Microvellum Processing Center Application
The standalone Processing Center application provides shop-floor tools for managing and executing manufacturing data generated from Microvellum projects. It enables users to: Print part labels View and print reports Create and re-create manufacturing ...
Microvellum Release Notes | Build 25.2.0213.641
The following release notes apply to Microvellum build 25.2.0213.641 File Name Fix An issue was occurring when processing work orders with the Create Sequential File Names setting enabled. When the setting was enabled, a work order being processed ...
Microvellum Release Notes | Build 25.2.0206.641
The following release notes apply to Microvellum build 25.2.0206.641. Item Number Fix An issue was reported regarding item numbers in composite drawings. Users who processed work orders with multiple products reported that the item numbers would ...