HBore Toolfile Fix

Fig. 1: The location in the Toolfile UI where the error would occur.
  1. There was an issue reported with the functionality of the Horizontal Boring Machine setting in Toolfiles; namely, when attempting to set a Toolfile Machine Type to Horizontal Boring Machine within the Toolfile interface, users would encounter an error. This issue has been resolved; users should now no longer encounter any errors when setting the machine type within the Toolfile UI. 

MVProduction Fixes

There were a small number of issues reportedly encountered by users utilizing the MVProduction:
  1. When attempting to open reports within a project with “Display Cost Based Estimating” enabled, the report would not open, and the user would get an error. 
  1. When working with Purchase Orders within the MVProduction, attempting to print a Purchase Order would result in the order not displaying, and the user getting an error.
  1. When users attempted to open older existing estimating reports in MVProduction, they would sometimes encounter an error stating that the report requires a work order to be open.
  1. All these issues have been resolved- using or attempting to use purchase orders and reports should no longer result in any errors within MVProduction. 

Polyline Pocket Routing Fixes

  1. Users reported issues that would occur when attempting to route with a polyline token:
Fig 2: Edge profiles dropped from a product (left) and restored (right).
  1. Products and parts with a polyline token would sometimes lack or not apply an edge profile to the part or product. 
Fig. 3: Corner routes disappearing from a part (left) and displaying correctly (right).
  1. Corner routes would sometimes fail to draw or be added onto their assigned parts or products. 
  2. Toe kicks that were pocketed using a CORNERNOTCH token would sometimes not display their routing or pocketing type correctly. 
Fig. 4: Cleanup routes being dropped (left) and appearing correctly (right).
  1. When drawing cleanup routes (routes outside of the part borders intended to be used to clean out material prior to mitre or profile cutting) in 2D, users sometimes would encounter an issue where the routes outside of the border would be dropped entirely. 
  2. All these issues were occurring because polylines of routes were 100% off the part. It was the standard that the route would be dropped from the part entirely. With this update, a part border will be detected by the software, and if it is within 1.5x the bit diameter, the route will no longer be dropped. With this change, all these issues should be resolved and no longer occur.


    • Related Articles

    • Toolbox Release Notes | Build 21.1.0714.641

      The following Release Notes apply to Toolbox Build 21.1.0714.641 Include Routes in Borders (IRIB) Improvements have been made to the Include Routes in Borders (IRIB) functionality of Toolbox.   This means increased accuracy and faster processing of ...
    • Toolbox Release Notes | Build 21.1.0827.641

      The following Release Notes apply to Toolbox Build 21.1.0827.641 Estimating Modifications: Modified the "Product Cost Details" command.  The Estimate Price will now access the database value for sheet stock, solid stock, buyout, edge band, and ...
    • Toolbox Release Notes | Build 21.1.0916.641

      The following Release Notes apply to Toolbox Build 21.1.0916.641 User Interface Additions: Added a minimum window size and a maximize window control to many user interface windows including Part Properties, Product Prompts, Edit Design Data, and ...
    • Toolbox Release Notes | Build 21.1.1119.641

      The following Release Notes apply to Toolbox Build 21.1.1119.641 Database Management This build features significant development focused on improving the user experience with Toolbox's Database Management utility.  The following updates and defect ...
    • Toolbox Release Notes | Build 24.1.1105.641

      The following release notes apply to Toolbox build 24.1.1105.641 Nesting Fix Fig. 1: The fatal error that would occur during processing. There was reportedly an issue that occurred when clients attempted to process a work order using the nesting ...
    • Recent Articles

    • Toolbox Release Notes | Build 24.1.1206.641

      The following release notes apply to Toolbox build 24.1.1206.641 MV Server Nesting Fix There was a reported issue occurring when users attempted to remotely process work orders using a nesting station on MV Server. When attempting to process the work ...
    • Microvellum Foundation Library Release Notes | Build 24.1127

      The following release notes apply to Microvellum Foundation Library build 24.1127. Additions Added a new Soffit product to the Upper Cabinet Accessories category. Added the Top Filler (Ceiling Scribe) option to Upper and Tall cabinets. (Corner ...
    • Toolbox Release Notes | Build 24.1.1125.641

      The following release notes apply to Toolbox build 24.1.1125.641. IRIB Setmill Location Fix Fig. 1: Setmill being moved to the start of the route (top) rather than at the center of a straight line, as intended (bottom). There was an issue reportedly ...
    • Toolbox Release Notes | Build 24.1.1105.641

      The following release notes apply to Toolbox build 24.1.1105.641 Nesting Fix Fig. 1: The fatal error that would occur during processing. There was reportedly an issue that occurred when clients attempted to process a work order using the nesting ...
    • Microvellum Foundation Library Release Notes | Build 24.1025

      The following release notes apply to Microvellum Foundation Library build 24.1025. Additions Added new global variable “Remove Stop Dado On Bottom Edge” for wood drawer boxes. Check this option to run the dado through at the bottom of the sub front ...